Beşiktaş Vodafone Park Stadium
Stadium membrane roofing — manufacturing & installation
At Beşiktaş Vodafone Park Stadium in Istanbul, ETNA completed the manufacturing and installation of 30,000 m² of stadium membrane roofing in a total of 49 days. The duration covers both manufacturing and installation, not installation alone.
Manufacturing and installation scope
The project brings together large-scale membrane roof manufacturing and engineering-led installation under a demanding construction schedule. It demonstrates ETNA’s production capacity and practical experience with complex stadium roofing systems.
The existing project record identifies PTFE, silicone and transparent membrane roof coverings. The original project photographs remain part of the gallery.
- Istanbul, Türkiye
- 30,000 m² of membrane roofing
- 49 days: total manufacturing and installation