Stadium membrane roofing — manufacturing & installation

At Beşiktaş Vodafone Park Stadium in Istanbul, ETNA completed the manufacturing and installation of 30,000 m² of stadium membrane roofing in a total of 49 days. The duration covers both manufacturing and installation, not installation alone.

Manufacturing and installation scope

The project brings together large-scale membrane roof manufacturing and engineering-led installation under a demanding construction schedule. It demonstrates ETNA’s production capacity and practical experience with complex stadium roofing systems.

The existing project record identifies PTFE, silicone and transparent membrane roof coverings. The original project photographs remain part of the gallery.

  • Istanbul, Türkiye
  • 30,000 m² of membrane roofing
  • 49 days: total manufacturing and installation

Related solutions

Contact our engineering team · Request a quotation

Project Information
Sports Facilities
2016
Turkey
Roof,
Arc,
A>20000 m2 ,
Membrane Roof System,